|
In 1998 the Joint Venture Semiconductor
300 (Infineon/Motorola) installed the
world’s first 300 mm Pilotline at the existing
Infineon Dresden facilities. The goal of this
JV was to prove 300mm readiness for tool
and process, automation and
manufacturing. After the first product
qualification in 99 and a fast ramp yield
more than 10 million DRAMs (64M, 128M)
have been shipped from this pilotline to the
customer. For this 300mm breakthrough,
SEMI’s Fab of the year award 2000 went to
Semiconductor 300.
The Start Up phase of a new fab lasts from the final stage of construction/
infrastructure until the installation of the first and the back up toolset. Due to the complexity and the interdependence of concurrent systems and activities, this phase is normally a major challenge, even in a classical 200mm environment. For 300mm the complexity increases. There are additional built in strong links between construction, automation, hook up and equipment.
The Start Up phase of a new fab lasts from the final stage of construction/
infrastructure until the installation of the first and the back up toolset. Due to the complexity and the interdependence of concurrent systems and activities, this phase is normally a major challenge, even in a classical 200mm environment. For 300mm the complexity increases. There are additional built in strong links between construction, automation, hook up and equipment.
Besides the technical challenges for an efficient 300mm start up in time, quality and cost, three key success factors have been proven to be mandatory:
• team approach,
• appropriate management methods,
• preparation and application of the necessary tools.
After a smooth Start Up last year, Infineon Technologies SC300 is currently ramping the world’s first 300mm memory fab with 256M DRAM in 140nm technology to high volume at Dresden/Germany.
Seven Field Map

THE Seven Field Map is a methodology, developed
by BQI Consulting Limited, to describe and visualise
business processes. It shows the responsibility for the
main process and the relations to corresponding sub
processes, it also provides the necessary information
regarding the input, output and deliverables of each
single process step. In addition, it links the overall
controlling process to the sub processes.
The Seven Field Map facilitates complicated tasks
by providing transparency, to all involved parties, and
highlighting different responsibilities along the
process, t. |
Team Approach
During the Start up phase interest conflicts in goal setting and resource availability are typical.
The general contractor has to finish base built and installation to achieve the milestone Ready for Equipment (RfE). The hook up management has to prepare the tool installation. Production and Facility people become familiar with the results of an extended planning, which had been performed months before. Clashes in the installation of base built and hook are inevitable. This is usually the time of conflict situations, which results in task forces, delays and additional costs,
The Fab of the Future team accumulated the experience of construction and Start Up of more than four 200mm Infineon and JV fabs in Europe, US and SEA in the 90th. This professional team included as well the consultants (SIBC, SHK) the general contractor (MWZ) for construction, infra-structure and hook up. A one team approach was defined from the very beginning, with a clear understanding of common and of mutual responsibilities. Despite all upcoming conflicts in the Start Up Phase, immediate solution oriented decisions and proceeding could be achieved.
But even assuming a perfect team has been assembled, the Start Up Phase also requires a set of management methods. These are clear common goals, full transparency of business processes, and tools to support the decision and controlling process.
Management Methods
Goal setting
Before groundbreaking the Fab of the Future team had defined all necessary milestones with detailed deliverable descriptions from construction/infra until the Start Up Phase. These (26) milestones were the unique base for a consistent set of goals for all activities during the whole project. The corresponding status reports using MTAs (Milestone Trend Analysis) were valid for all team members and partners, defining as well incentive and bonus programs.
Tool Alignment

THE Automated Material Handling System
provides FOUP storage, interbay transport
between process areas across several building
as well as intrabay transport (direct tool
loading) into a subset of process areas via an
OHT system. OHT for direct tool for
equipment move in. To guarantee the exact
equipment handshake between FOUP and
loadport, the AMHS and the Equipment have
to be aligned to plus minus 0.5 cm. A laser
measurement based tool-alignment process
was developed, allowing even to align a
stepper of 20 tons weight within this very
small tolerance. To manage this highly
sensitive process, a lasergrid with a tolerance
of 1mm over the whole fab has to be built up.
This allows the alignment of all foundations,
templates and equipments to the virtual tool
alignment line. It is preferable to have the
AMHS installed and running before the move
in of the equipment. The tool alignment line
is defined in the Semistandard E15.1. |
Equipment Database

THE Equipment Database is a Infineon
proprietary online application to support the
planning of the Equipment provision. It contains
the backwards calculated planned dates for
shipping, move in, hook up, process and
hardware start up and compares those to the
actual dates. Deviations and the resulting impact
on the forward calculated ready for production
date can be seen immediately. This tool allows to
track the complete start up process along all the
process steps with respect to the Project plan and
– if necessary – to take the right corrective actions. |
Business process approach
During the Start Up Phase of a big new Fab, usually more than 1000 people work under heavy time pressure in concurrent, interdependent and overlapping activities. To be able to manage this phase successfully, early planning and preparation work is essential. The 300mm Start Up Team has been installed nine months before the RFE-date. All necessary business processes have been defined and documented with the so-called Seven Field Maps (see Box Seven Field Map). This business process approach describes sequences, relationships, deliverables and responsibilities. The maps were defined with those responsible and communicated to all key participants. But to manage the interfaces between the process steps, an organised communication structure is mandatory.
Communication structure
The communication structure followed the Seven Field Map approach. Participants, input, output, content, goals, responsibilities, dependencies and frequencies of the meetings have been defined to build a self-controlling system. Three examples may demonstrate the principle:
1. With a well defined preparation, the so-called cascade meetings allowed to update all hook up relevant information in a database within two days for the total fab. Performed on regular time base, surprises during the Start Up process have been reduced to a minimum.
2. During the weekly move in meeting a two week forecast was frozen and communicated. A buffer storage for the incoming equipment always guaranteed a smooth move in.
3. Regular management project meetings of general constructor, consultants and Infineon ensured the focus to common goals with final decisions.
Hook up

General Contractor
Hook-up
Organisation
The project organisation had to match the team
structure, which was set up for the entire project
including the clients facilities and equipment
engineers. To develop a ‘hook-up team spirit’
was an essential step in the right direction to
finish this project successfully.
A matrix organisation ‘set-up’ between
equipment engineer, hook-up designer, facility
engineer, hook-up supervisor and consultants
was the key to succeed during the fast track
ramp-up phase.
Installation
The installation process was divided into three
Phases:
Hook-up 0:
Pre-fabrication in remote workshops. Because of
limited space on site, the subcontractors had no
opportunity to place storage and prefabrication containers directly on site.
During the Hook-up 0 Phase, the first tool
information have been handed over via design
book by the client to the M+W Zander tagging master. Those documents enabled the base
built design team to react and optimise the base
built detail design.
With the available tool information, a
loading limit check through all systems was
done in parallel. (Figure 1)
Hook-up 1
Beginning of pre-installation in the clean room.
In accordance to the ‘move in’ plan, M+W
Zander located the subcontractor preinstallation
areas in the sub-fab area.
Prior to tool arrival, such installations like
those shown in Figure 2, below, were already
done.
To realise a pre-installation for all major
tools, a bright information loop between client,
‘move in’ team, M+W Zander and
subcontractors was established. The main focus
was that the 2D and 3D templates, to support
the pre-installation, 2-4 weeks prior of ‘move in’
on site.
 Figure 2. Template 3D ASML Furnace.
|
Conflict prevention
In the Start Up Phase, unattended conflicts are expensive and delay the project. Having enough experience, it is very possible to preview potential conflicts before they happen. Two examples may demonstrate:
1. Monitoring the resource planning for dedicated hook up specialists weeks before work execution, it was possible to detect and resolve future capacity and schedule problems before they had any impact.
2. Equipment decisions had to be later in some cases than the base built installation definition. Therefore a consistent planning of base built and hook up installation was not possible ahead. But there was a small time window before prefacilitation to perform a mutual fit of both installations with little influence on time and cost.
In addition to the team approach with these and other management methods, specific Start Up tools are mandatory to handle the complexity. One major task of the Fab of the Future project from 1998 to 2001 was the evolution of existing hardware and software tools and the development of new tools for the 300mm Start Up Phase.
Tool preparation and application
From the 200mm experience the Equipment Data Base and hook up procedure have been adapted and further developed. Main new tools for 300mm are the Tool Alignment and the Media Consumption Measurement system (MCM).
Equipment Data Base
This tool is the planning and controlling base for all equipment activities and their scheduling (see Box Equipment Data Base) from planning start until the process qualification during the Start Up. It has matured with several new fabs.
An exchange server was installed, providing all equipment and project documents online for each accepted ‘user’. A link of all databases and tools and the summary of all relevant data under a practical User Interface called System Matrix was installed.
Hook up
Six months before RfE, the equipment list was defined and the layout was frozen. Matching this information, the media design could be checked in detail. A tagging list with all submain to tool correlations showed up the necessary adjustments. Before RfE all adjustments were ready. During the hook up period no major changes occured. (Frank Mattukat, Stephan Migge, MW-Zander, Micromagazine Facility Technology, September 2000 – see the panal entitled Hook up). With a pre-installation period of six weeks, hook up duration times were optimised. The stocker of the transport system were moved in four weeks before RFE.
Hook up (continued)

Figure 3. Template 3D ASML Furnace.

Figure 4. Space management Subfab
Hook-up 2
During this phase of the project,
services to the process equipment and
their corresponding sub-tools will be
finally connected to the facilities. This
includes testing, commissioning,
acceptance and release to the owner. |
Tool Alignment
For a successful pre-installation two and three dimensional templates were used (see Pictures of ASM, TEL, CENTURA). Since the Automated Material Handling System requires an accuracy of plus/minus 0.5 cm per tool, a tool alignment process was developed. All fundamentals and templates have to be positioned exactly to this alignment line. (see Box Tool Alignment)
|
300mm Infineon Start-up with SemiSoft
SemiSoft is fully integrated in the startup of the Infineon Technologies 300mm volume production in
Dresden. The SemiSoft consultants and engineers started from the early beginning of the pilot line
phase to investigate most realistic system consumption figures for 300mm equipment. The real
consumption data was measured with sensors, such as mass flow meters or ultrasonic sensors in the
Hook-up lines as well as transmitted via the SECS II interface of the equipment or generated from
cumulated recipe date linked with the actual production data. An online data link to the manufacturing
execution system (MES) allowed to understand the measured system consumption data in relation to
the actual used production capacity for every single supply-system such as chemicals, gases and also
power , exhaust or cooling water on every equipment. The data link to the various data sources are the
basis for the worldwide first 300mm supply-system database with real measured consumption. Based
on this unique data base the SemiSoft team could generate a very precise projection for the 300mm
mass production line. With data links to the MES System, the process recipe database, the equipment
move-in database and the CADLayout
the SemiSoft team generated
supply-system ramp up curves,
supply-system layouts and supplysystem
budget plans. Based on this
information Infineon could design a
optimized, custom-made supply
system infrastructure. The SemiSoft
products and services are also an
important success factor for the fast
track Start-up project. In the running
Fab the SemiSoft SystemMatrix is in
operation as supply-system database
including energization tracking for
every single Sub-main interface.
SemiSoft® is the trademark project
management, engineering and software
design of SHK. SHK is a team of young,
highly motivated specialists working to
support their clients projects during the
construction, ramp up, and mass production
phases of leading edge wafer front-end
production lines. For more information
please refer to www.SemiSoft.de and
www.SHK.com.
|
|
Media Consumption
Measurement System MCM
One focus of the 300mm Pilotline project was to generate information about the Media Consumptions of 300mm equipments. Several hundred sensors were installed and the data were administrated by SemiSoft SystemMatrix. This valuable data were used to calculate the Media consumption of the 300mm fab with the frozen equipment list. In combination with the tagging list this design check highlighted the few necessary adjustments before final installation. The MCM sensors have been installed now in the 300mm production to provide a full reference tool set. The SemiSoft SystemMatrix is in full operation and supports the ramp of the Fab. Media Consumption will be monitored to support planning, environment and productivity programs.
Conclusion
“In the end, all business operations can be reduced to three words:
people, products and profits.
Unless you’ve got a good team, you can’t do much with the other two.”
Lee Iacocca
Using the above mentioned methods and tools, the team has successfully performed the first 300mm volume Start Up. The initial product, the world’s smallest 256M DRAM on the biggest wafers is qualified. The market conditions for memories have been tough. For the profits, 300mm has an intrinsic advantage of a productivity advantage up to 30%.
Most importantly, a team approach has now been implemented for the volume ramp of the fab.
|